Title
Hunter Contracting Co.
Description
For $1,146,180 in additional payment authority for Contract 153785 Change Order 1 (WS90500295-5), Relief Sewer Project - Van Buren and 52nd Streets, for the Water Services Department. The original contract included 500 lineal feet of hard rock trenching. The actual lineal footage of hard rock trenching encountered was 2,865 lineal feet. The increased quantity of hard rock trenching increased the project cost and project duration. This project uses Water Services Department Capital Improvement Program funds; no general funds are required.