File #: 18-2658   
Type: Ordinance-S Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 10/3/2018 Final action: 10/3/2018
Title: Steel Tank Rehabilitation Program Group J Fiscal Year 2018-19 - Construction Manager at Risk Construction Services Amendment 3 - WS85050023 (Ordinance S-45034)
District: District 2
Related files: 18-1190, 18-0654, 17-5171, 17-4076, 16-1057, 17-3341, 17-3847

Title

Steel Tank Rehabilitation Program Group J Fiscal Year 2018-19 - Construction Manager at Risk Construction Services Amendment 3 - WS85050023 (Ordinance S-45034)

 

Description

Request to authorize the City Manager, or his designee, to execute an amendment to Agreement 142402 with Felix Construction Company (Felix) to provide additional Construction Manager at Risk (CMAR) Construction Services for the Steel Tank Rehabilitation Program Group J Fiscal Year 2018-19 project. Further request to authorize execution of amendments to the agreement as necessary within the Council-approved expenditure authority as provided below, and for the City Controller to disburse all funds related to this item. The additional fee for services included in this amendment will not exceed $1.7 million.

 

Report

Summary

The purpose of the Program is to extend the service life of these assets, minimize water loss, and protect water quality and public health using a proactive approach. There are 42 steel tanks located at 33 different sites serving as potable water storage/pressure surge protection facilities within the City's water production and distribution system. The project includes maintaining the coating and structural integrity of these steel tanks, enhancing water quality (recirculation systems, mixing, disinfection system upgrades, etc.) associated with the steel tank sites, and providing site-related improvements including, but not limited to, erosion repair and upgrading fencing.

 

This amendment is necessary to expand the Construction Services for this Program to include Group J in the scope of the project for Fiscal Year 2018-19.

 

Felix's initial services for Group J will include preparation of a Guaranteed Maximum Price (GMP) proposal for the Construction Services provided under the agreement and participating with the City in a process to set a local and Small Business Enterprise (SBE) goal for the project. Felix will be responsible for construction means and methods related to the project and fulfilling the SBE program requirements. Felix will be required to solicit bids from prequalified subcontractors and to perform the work using the City's subcontractor selection process. Felix may also compete to self-perform limited amounts of work.

 

Felix's services for Group J include, but are not limited to: performing the designated rehabilitation of the reservoir tank and the surrounding site; replacing of tank fixtures and appurtenances; installation of new gates, and crack sealing asphalt.

 

Procurement Information

The selection was made using a qualifications-based selection process set forth in section 34-603 of the Arizona Revised Statutes. Scoring and selection were made in conjunction with the CMAR Preconstruction Services selection process.

 

Contract Term

The term of the agreement will be extended for an additional two years. Work scope identified and incorporated into the agreement prior to the end of the term may be agreed to by the parties, and work may extend past the termination of the agreement. No additional changes may be executed after the end of the term.

 

Financial Impact

  • The initial agreement for CMAR Construction Services was executed for a fee not-to-exceed $28,786.24, including all subconsultant and reimbursable costs.
  • Amendments 1 and 2 increased the agreement value by $5.2 million.
  • Amendment 3 will increase the agreement by an additional $1.7 million, for a new total not-to-exceed agreement value of $6,928,786.24, including all subcontractor and reimbursable costs.

 

Funding for this amendment is available in the Water Services Department's Capital Improvement Program budget. The Budget and Research Department will separately review and approve funding availability prior to execution of any amendments. Payments may be made up to agreement limits for all rendered agreement services, which may extend past the agreement termination.

 

Concurrence/Previous Council Action

The City Council approved:

  • CMAR Construction Services Agreement 142402 for Project Group H (Ordinance S-42429) on April 6, 2016.
  • Amendment 1 to Agreement 142402 for Project Group H (Ordinance S-42740) on June 22, 2016.
  • Amendment 2 to Agreement 142402 for Project Group I (Ordinance S-43782) on July 6, 2017.

 

 

Location

Tramonto Tank, Carefree Highway and Paloma Parkway

Council District: 2

 

Department

Responsible Department

This item is submitted by Deputy City Managers Karen Peters and Mario Paniagua, the Water Services Department, and the City Engineer.