Title
Hunter Contracting Co.
Description
For $1,450,000.00 in additional payment authority for Change Order 1, for Contract 140324, for Construction Manager At Risk construction services for the Water Services Department WS85200010 Verde WTP Facilities Demolition and Site Restoration project. The contract duration will not be impacted by this change order. After the construction started, arsenic soils were discovered in the vicinity of the abandoned percolation pond, requiring remediation. Remediation of the contaminated soils was not included in the original scope of work. Change Order 1 requests addition to the scope for removal and replacement of arsenic-contaminated soils in the area of the abandoned percolation pond.