Title
Salt River Project Distribution Design and Construction Contract for Lift Station 58 - WS90400092 (Ordinance S-50369)
Description
Request to authorize the City Manager, or his designee, to enter into a Distribution Design and Construction Contract with Salt River Project (SRP) for work associated with City of Phoenix project WS90400092, Lift Station 58 at 20th Street and Maryland Avenue. Further request the City Council to grant an exception pursuant to Phoenix City Code 42-20 to authorize inclusion in the documents pertaining to this transaction of indemnification and assumption of liability provisions that otherwise would be prohibited by Phoenix City Code 42-18. Additionally request to authorize the City Controller to disburse all funds related to this item. The total value of this contract will not exceed $29,347.
Report
Summary
The Water Services Department is constructing improvements to Lift Station 58 at 20th Street and Maryland Avenue which will require the design and construction of new electrical facilities. This contract represents the cost for Salt River Project’s design and construction of an upgraded transformer to provide additional power to the site. The work associated with this contract is in conjunction with City project WS90400092.
Contract Term
The contract will begin on or about Dec. 8, 2023, and will expire when the project is complete and accepted.
Financial Impact
Funding in the amount of $29,347 is available in the Water Services Department Capital Improvement Program budget.
Location
20th Street and Maryland Avenue
Council District: 6
Department
Responsible Department
This item is submitted by Deputy City Managers Ginger Spencer and Alan Stephenson, the Water Services Department and the City Engineer.