File #: 17-1946   
Type: Ordinance-S Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 4/5/2017 Final action: 4/5/2017
Title: Electrical, Instrumentation and Control Systems Inspection and Testing Services - Lift Stations - WS90400078-1 (Ordinance S-43389)
District: Citywide

Title

Electrical, Instrumentation and Control Systems Inspection and Testing Services - Lift Stations - WS90400078-1 (Ordinance S-43389)

 

Description

Request to authorize the City Manager, or his designee, to enter into a contract with Arcadis US, Inc., (Phoenix) to provide design support, construction inspections and commissioning testing in support of projects associated with electrical, instrumentation and control systems at 28 lift stations located throughout the City. Further request authorization for the City Controller to disburse all funds related to this item.

 

Report

Summary

The Water Services Department developed electrical, instrumentation, and control standards which are used to provide consistency and safety throughout the department.  Arcadis US, Inc.'s role will be to ensure adherence to these standards during design, construction, calibration, testing, and commissioning of the electrical, instrumentation, and control systems at lift stations throughout the City. In addition, Arcadis US, Inc., will provide operations and maintenance support when City staff are replacing existing equipment or installing new equipment, and may be required to provide arc flash hazard testing services.

 

Procurement Information

Eleven firms submitted for this qualifications-based selection process.  The City selected the top four ranked firms to perform the above services in various Water Services locations using a single procurement according to Section 34-604 of the Arizona Revised Statutes (ARS).  The firm rankings are listed below:

 

Black & Veatch Corporation: Ranked #1

OZ Engineering: Ranked #2

Brown and Caldwell, Inc.: Ranked #3

Arcadis US, Inc.: Ranked #4

Wilson Engineers, LLC.: Ranked #5

Stanley Consultants, Inc.: Ranked #6

Greeley and Hansen, LLC.: Ranked #7

Westin Engineering, Inc.: Ranked #8

Industrial Power Solutions, LLC.: Ranked #9

Quantum: Ranked #10

Automation Controls Design Specialists, LLC.: Ranked #11

 

Per ARS Title 34, the City is not to release the scoring of proposers until a contract has been awarded.

 

Contract Term

The term of the contract is four years. Contract work scope identified and incorporated into the contract prior to the end of the contract may be agreed to by the parties, and work may extend past the termination for work in progress. No additional contract work scope changes may be executed after the end of the contract term.

 

Financial Impact

Arcadis US, Inc.’s fee will not exceed $1,250,000 for the total four-year contract, including all subconsultants and reimbursable costs. Funding is available in the Water Services Department’s Capital Improvement Program. Contract payments may be made up to contract limits for all rendered contract services, which may extend past the contract termination.

 

Department

Responsible Department

This item is submitted by Deputy City Managers Karen Peters and Mario Paniagua, the Water Services Department, and the City Engineer.