File #: 18-0544   
Type: Ordinance-S Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 4/18/2018 Final action: 4/18/2018
Title: Water Production Wells and Aquifer Storage Recovery Wells - Program Management Services Phase I Amendment - WS85010054-2 (Ordinance S-44465)
District: District 1, District 2, District 3
Related files: 17-2769, 17-3366, 17-3367, 17-3368

Title

Water Production Wells and Aquifer Storage Recovery Wells - Program Management Services Phase I Amendment - WS85010054-2 (Ordinance S-44465)

 

Description

Request to authorize the City Manager, or his designee, to execute an amendment to increase the value of Contract 145495 with Carollo Engineers, Inc. to provide Program Management Services in support of design and construction of production wells and Aquifer Storage Recovery (ASR) wells. Further, request authorization to execute amendments to the contract as necessary within the Council approved expenditure authority as provided below, and for the City Controller to disburse all funds related to this item. The fee for additional services will not exceed $820,000.

 

Report

Summary

The City is designing and constructing four production wells and six ASR wells by 2021. Water pumped from the wells will be used to supplement water resources during times of long-term water shortages, emergency outages, and to meet water system demand balancing.

 

Carollo Engineers, Inc.'s services include: organizing, coordinating, and providing technical advice; and overseeing the necessary resources required to conduct the design, construction, permitting, public communications, and initial operations of production and ASR wells. Carollo Engineers, Inc. will ultimately be responsible for assisting the Water Services Department with planning and implementation of the well program.

 

This increase in contract value is necessary to expand the capacity of the Program Management Services contract to include scope of work for construction-related services as well as design services that were approved by Council on June 28, 2017.

 

Procurement Information

Carollo Engineers, Inc. was chosen for this project using a qualifications-based selection process according to section 34-603 of the Arizona Revised Statutes.

 

Contract Term

The term of this contract is expected to coincide with the duration of Phase I of design and construction, which is expected to be completed by 2021. Contract work scope identified and incorporated into the contract prior to the end of the contract may be agreed to by the parties, and work may extend past the termination of the contract. No additional contract work scope changes may be executed after the end of the contract term.

 

Financial Impact

The initial contract value was established at a not-to-exceed amount of $2,000,000. If approved, this amendment would increase the contract amount by $820,000, including all subconsultant and reimbursable costs, for a new total contract value of $2,820,000. Funding is available in the Water Services Department's Capital Improvement Program budget. Contract payments may be made up to contract limits for all rendered contract services, which may extend past the contract termination.

 

Concurrence/Previous Council Action

The City Council approved:

  • Program Management Services Contract 145495 (Ordinance S-43707) on June 28, 2017;
  • Engineering Design Services Contracts 145611-145613 (Ordinance S-43784) on July 6, 2017;
  • Construction Manager at Risk Design Phase Services (Ordinance S-43783) on July 6, 2017; and
  • Construction Manager at Risk Construction Phase Services (Ordinance S-43968) on Oct. 18, 2017.

 

Location

Various

Council Districts: 1, 2, 3

 

Department

Responsible Department

This item is submitted by Deputy City Managers Karen Peters and Mario Paniagua, the Water Services Department, and the City Engineer.