Title: PCL Construction, Inc.

Title

PCL Construction, Inc.

 

Description

For $640,000.00 in additional payment authority for Contract 144567, Change Order 1 (Project WS85500443-1) for construction manager at risk services for the Thomas Road Transmission Main Rehabilitation project for the Water Services Department. This change order request includes anticipated cost adjustments based on actual project spending and also allows for an additional 24-inch pipe connection for Remote Facilities Booster Pump Station 2A-B9 and 2C-B3 at the 52nd Street Yard. This additional connection will facilitate future improvements to the booster station site under Project WS85400007 for the Water Services Department.