Title
AJP Electric, Inc.
Description
For $42,500.00 in additional payment authority for Agreement 148621, for Change Order 1 Project ST89330183 for FY2018 Federal TAP HAWK Installation for the Street Transportation Department. The additional funds cover additional construction work and additional time necessary to complete the project as the contractor encountered several issues that included: conflicts with design plans, unforeseen field conditions, right-of-way restrictions outside the normal practices, water leaks, up-sizing of traffic signal poles; and utility relocation and, or coordination.