Legislation Details

File #: 22-2064   
Type: Discussion and Possible Action Status: Agenda Ready
Meeting Body: Transportation, Infrastructure, and Planning Subcommittee
On agenda: 11/16/2022 Final action:
Title: Transition to Zero Emission Heavy-Duty Bus Fleet
District: Citywide

Title

Transition to Zero Emission Heavy-Duty Bus Fleet

 

Description

This report requests the Transportation, Infrastructure and Planning Subcommittee recommend City Council approval of the Public Transit Department’s Heavy-Duty Bus Purchasing Strategy and Zero Emission Fleet Transition Plan for the next five years to advance the City toward a goal of achieving a 100 percent zero-emissions bus fleet by 2040.

 

THIS ITEM IS FOR DISCUSSION AND POSSIBLE ACTION.

 

Report

Background

The City of Phoenix Public Transit Department (PTD) provides public transportation for approximately half of the Phoenix metropolitan area, including 38 local bus routes, four circulator routes, and six RAPID (commuter) routes. PTD’s heavy-duty fleet is comprised of 500 40- and 60-foot buses, all of which are powered with cleaner-burning fuels (335 compressed natural gas (CNG) and 165 biodiesel).

 

Under Council’s direction, PTD has worked over the years to ensure its fleet has the most up-to-date, environmentally friendly buses with the best proven technology available, which at the same time have shown the ability to operate in Phoenix’s harsher climate. Key factors include range (how far buses can travel) and operations during Phoenix’s extreme summer temperatures (ensuring that buses have robust air conditioning and available power for multiple on-board systems to provide a high-quality passenger experience year-round). These considerations remain at the forefront of departmental decision-making as the City transitions to a greener, more sustainable heavy-duty transit fleet.

 

Summary

In January 2022, City Council approved the issuance of a solicitation that allows PTD to implement an initial five-year plan to operate a sub-fleet of near-zero and zero emission heavy-duty buses, during which time staff will evaluate the performance of newer charging/fueling technologies and propulsion systems.

 

To advance PTD’s goal to begin converting its heavy-duty transit fleet to 100 percent zero-emissions buses (ZEB) by 2040, a bus replacement plan and infrastructure phasing strategy will guide the long-term planning and capital improvement project goals. Key considerations that factor into the long-term mix of ZEBs in PTD’s fleet are: i) additional federal and regional funding commitments for the purchase and maintenance of capital assets, as transit vehicles are 85% federally funded and 15% regionally funded;  ii) evaluation of the year-round performance of Battery Electric Buses (BEB) and Fuel-Cell Electric Buses (FCEB) in our climate; iii) vehicle production timelines, which currently estimate longer lead times for newer-technology buses and shorter lead times for existing technologies; and iv) commitments to transit passengers and our contracted service providers to continue the acquisition of new vehicles to ensure the resiliency of the transit fleet and to keep maintenance costs low.

 

As a result, PTD’s ZEB transition plan is envisioned to occur in two phases:

  • Phase I - FY 2023-27: PTD will begin purchasing BEB and FCEB vehicles to initiate the acquisition and testing of the city’s ZEB sub-fleet, while also purchasing a mix of hybrid-electric and CNG-fueled buses in the initial years to ensure the fleet continues to provide a reliable service year-round for our transit riders. The acquisition of low-emission (natural gas) buses will be phased out within the first three years of the plan. As part of citywide efforts to begin transitioning City fleets to electric vehicle options, a facilities and infrastructure study has also been initiated as part of Phase I to determine the needs of current and future transit facilities. Staff will return to Council with detailed information and costs regarding these capital investments at a later date. As a result, the facilities and infrastructure study will provide a cost estimate for our CIP program. Phase 1 includes infrastructure improvements in order to fuel the ZEBs, which is anticipated will be partially funded through the Bipartisan Infrastructure Law.
  • Phase II - FY 2028-40: Once the evaluation of ZEB vehicles is complete, PTD will continue the conversion of the heavy-duty fleet to 100 percent ZEBs.

 

Procurement Information

PTD and Finance Department staff have been working to procure new ZEBs through a cooperative purchasing agreement with Washington state. Additionally, an RFP was issued earlier this year for the purchase of ZEBs. Both the Washington state cooperative and the RFP process are expected to be completed by first quarter 2023. During this process, PTD staff was informed by various bus manufacturers that no ZEBs or HEBs can be delivered prior to calendar year 2025 due to ongoing supply chain disruptions and the resulting backlog of buses already ordered. Due to these lead times, PTD has adjusted its bus procurements to ensure the arrival of buses as quickly as possible to maintain the existing fleet by replacing buses that have met the end of their useful life.

 

Bus costs: Current estimated costs for each bus type are as follows:

  • 40’ CNG - $551,000
  • 40’ Hybrid-Electric Bus (HEB) - $750,000
  • 40’ Battery-Electric Bus (BEB) - $1.1 million
  • 40’ Fuel Cell Electric Bus (FCEB) - $1.2 million

 

The following is a projected schedule of replacement bus purchase orders during Phase I:

 

FY 22/23

  • 40’ BEB - 6
  • 40’ FCEB - 6
  • 40’ HEB - 20
  • 40’ CNG - 18

Total estimated cost: $38.7 million for 50 buses

 

FY 23/24

  • 40’ BEB - 6
  • 40’ FCEB - 6
  • 40’ HEB - 25
  • 40’ CNG - 17

Total estimated cost: $41.9 million for 54 buses

 

FY 24/25

  • 40’ BEB - 10
  • 40’ FCEB - 10
  • 40’ HEB - 8
  • 40’ CNG - 0

Total estimated cost: $29 million for 28 buses

 

FY 25/26

  • 40’ BEB - 10
  • 40’ FCEB - 10
  • 40’ HEB - 8
  • 40’ CNG - 0

Total estimated cost: $29 million for 28 buses

 

FY 26/27

  • 40’ BEB - 12
  • 40’ FCEB - 20
  • 40’ HEB - 8
  • 40’ CNG -0

Total estimated cost: $43.2 million for 40 buses

 

At the completion of Phase 1, PTD’s zero/near-zero fleet will consist of the following:

  • 69 hybrid electric buses
  • 44 battery electric buses
  • 52 fuel cell electric buses

 

By the end of Phase 1, PTD will have purchased 96 ZEBs and 69 hybrid-electric buses, accounting for one-third of the total fleet, with additional plans for ZEB infrastructure at both the South and West bus operations and maintenance facilities to support these new vehicles. For the first two years of Phase I, PTD will reduce its typical annual order of 40 CNG buses to 18 and 17, respectively. However, given the long lead times for the delivery of ZEBs and HEBs, PTD may need to retain a contingent of CNG buses beyond their useful life until ZEB and HEB replacements are received. This is due to the fact that lead times for the manufacture and delivery of CNG buses is between 12 to 14 months, while ZEB and HEB lead times are over 24 months.

 

Phase 2 of the plan will not include the purchase of any low-emission (i.e., natural gas) buses, but will focus on the continued acquisition of ZEBs. All procurements starting in FY2028 will be ZEBs and ZEB-related infrastructure, with the specific ZEB bus types to be determined following the results of the Phase 1 evaluations and anticipated technological improvements in ZEB range and efficiency.

 

Financial Impact

The anticipated cost of buses ordered during Phase I is $182 million: $19.3 million for CNG, $51.8 million for HEB, $48.4 million for BEB, and $62.4 million for FCEB. Buses are funded with federal and regional funds.

 

Location

Council Districts: Citywide

 

Department

Responsible Department

This item is submitted by Deputy City Manager Mario Paniagua and the Public Transit Department.