File #: 22-1755   
Type: Ordinance-S Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 5/3/2023 Final action: 5/3/2023
Title: 91st Avenue Wastewater Treatment Plant Solids Rehabilitation Phase 1 - Engineering Services Amendment 1 - WS90100111 (Ordinance S-49634)
District: District 7

Title

91st Avenue Wastewater Treatment Plant Solids Rehabilitation Phase 1 - Engineering Services Amendment 1 - WS90100111 (Ordinance S-49634)

 

Description

Request to authorize the City Manager, or his designee, to execute an amendment to Agreement 152491 with Arcadis U.S., Inc. to provide additional Engineering Services for the 91st Avenue Wastewater Treatment Plant Solids Rehabilitation Phase I project. Further request to authorize execution of amendments to the agreement as necessary within the Council-approved expenditure authority as provided below, and for the City Controller to disburse all funds related to this item. The additional fee for services included in this amendment will not exceed $5 million.

 

Report

Summary

The purpose of this project is to rehabilitate the facilities and equipment used to treat and process solids at the 91st Avenue Wastewater Treatment Plant (WWTP) including replacement of equipment throughout the solids treatment process.

 

This amendment is necessary to increase the contract value and contract term for the completion of construction administration and inspection services for the project. This amendment adds funding and time to the existing agreement.

 

The 91st Avenue WWTP is owned by the Sub-Regional Operating Group (SROG) and operated by the City of Phoenix.

 

Contract Term

The term of the agreement amendment is five years from the issuance of the Notice to Proceed. Work scope identified and incorporated into the agreement prior to the end of the term may be agreed to by the parties, and work may extend past the termination of the agreement. No additional changes may be executed after the end of the term.

 

Financial Impact

  • The initial agreement for Engineering Services was approved for an amount not-to-exceed $5,430,000, including all subconsultant and reimbursable costs.
  • This Amendment will increase the agreement by an additional $5 million for a new total amount not to exceed $10,430,000, including all subconsultant and reimbursable costs.

 

Funding for this amendment is available in the Water Services Department's Capital Improvement Program budget.

 

Concurrence/Previous Council Action

  • The SROG Advisors authorized the project on June 10, 2020.

 

The City Council approved:

  • Engineering Services Agreement 152491 (Ordinance S-46821) on July 1, 2020.

 

Location

91st Avenue Wastewater Treatment Plant

Council District: 7

 

Department

Responsible Department

This item is submitted by Deputy City Managers Ginger Spencer and Alan Stephenson, the Water Services Department and the City Engineer.