Request Authorization to Enter into Agreement with Arizona Public Service for Shaw Butte Mountain Access Tower Road Drainage Improvements (Ordinance S-47218)
Description
Request to authorize the City Manager, or his designee, to enter into an Agreement with Arizona Public Service (APS) for the Shaw Butte Mountain Access Tower Road Drainage Improvements Project, including the project administration, design, construction, construction management, operations and maintenance of the project. Further request to authorize the City Treasurer to accept, and the City Controller to disburse, all funds related to this item. The estimated project cost is $80,000, of which APS’s cost-share is estimated to be $20,000 with the remainder of the cost anticipated to be reimbursed by the Flood Control District of Maricopa County (FCDMC) under a separate agreement.
Report
Summary
The project consists of a new containment berm along the north edge of the Shaw Butte Mountain Service Tower Access Road, extending the existing containment berm easterly to the wash at the Shaw Butte Trailhead entrance. The proposed containment berm has a four-foot wide top width with side slopes along the access road. Floodplain Management staff is recommending the Shaw Butte Mountain Service Tower Access Road Drainage Improvement Project be completed through a funding partnership between the City, FCDMC and APS. The Shaw Butte Mountain Service Tower Access Road is primarily used by Maricopa County and APS.
Financial Impact
The overall project cost is approximately $80,000. APS’s cost-share is $20,000 and the remaining $60,000 would be funded by a separate agreement between the City and FCDMC.
Concurrence/Previous Council Action
The Transportation, Infrastructure and Innovation Subcommittee recommended City Council approval of:
- Entering into agreements with Maricopa County and APS for the Shaw Butte Mountain Service Tower Access Road Drainage Improvement Project on Oct. 7, 2020, by a vote of 4-0; and
- Maricopa County Fiscal Year 2021-22 Small Project Assistance Program on Oct. 7, 2020, by a vote of 4-0.
A separate request to enter into an Intergovernmental Agreement with the Flood Control District of Maricopa County for Shaw Butte Mountain Access Tower Road Drainage Improvements is being separately recommended to City Council for approval.
Location
The Shaw Butte Mountain Access Tower Road Drainage Improvement Project is located just west of Central Avenue and Wood Drive.
Council District: 3
Department
Responsible Department
This item is submitted by Deputy City Managers Karen Peters, Inger Erickson and Mario Paniagua, and the Public Works, Parks and Recreation and Street Transportation departments.