Proposal to Implement First Five Years Transportation 2050 New and Expanded Major Streets Lifecycle Program (Resolution 21530)
Description
Request City Council approval of the Transportation 2050 New and Expanded Major Streets Lifecycle Program (FY2018-2034) and to proceed with implementation of major street improvement projects identified in the first five years of the program (FY2018-2022).
Report
Summary
The Transportation 2050 (T2050) New and Expanded Major Streets Lifecycle Program covering fiscal years (FY) 2018 - 2034 identifies 45 individual projects to implement over this planning period (Attachment A). In total, the estimated costs to complete the identified projects is approximately $206 million. The Lifecycle Program includes project scopes that build-out each corridor to the ultimate roadway cross-section to improve aesthetic consistency, facilitate safer streets, and to support existing or planned transit operations.
Although the proposed Lifecycle Program covers a period through fiscal year 2034, staff recognizes that changing conditions and priorities may require adjustments to the Lifecycle Program. Staff recommends that the T2050 New and Expanded Major Streets Lifecycle Program be used to identify specific projects for implementation over a five-year period, with updates conducted on an annual basis.
The proposed five-year program covering FY2018-2022 aligns with the City’s Five-Year Capital Improvement Program and includes 26 projects totaling $57.3 million (Attachment B). If approved, staff would move forward with project development, which would include final design, right-of-way acquisition, and construction.
Financial Impact
The proposed five-year program covering FY2018-2022 (Attachment B) aligns with the City’s Five-Year Capital Improvement Program and includes 26 projects totaling $57.3 million.
Concurrence/Previous Council Action
The Transportation and Infrastructure Subcommittee recommended City Council approval of this item on March 14, 2017. The Citizens Transportation Commission recommended T&I Subcommittee and City Council approval of this item on Feb. 23, 2017.
Location
Locations of the new and expanded major streets projects in the five-year program (FY2018 - 2022) include: Baseline Road: L202/59th Avenue to 55th Avenue; Buckeye Road: 67th Avenue to 59th Avenue/Loop202; Indian School Road: 99th Avenue to 91st Avenue; Indian School Road: 107th Avenue to 99th Avenue; Lower Buckeye Road: 27th Avenue to 19th Avenue; Lower Buckeye Road: 35th Avenue to 27th Avenue; Baseline Road: 46th Avenue to 43rd Avenue; 91st Avenue: Indian School to Thomas Road; 91st Avenue: Buckeye Road to Lower Buckeye Road; Lower Buckeye Road: 83rd Avenue to 75th Avenue; Lower Buckeye Road: 91st Avenue to 83rd Avenue; 16th Street and Indian School Road; 35th Avenue: Bethany Home Road to Camelback Road; 35th Avenue: Glendale Avenue to Bethany Home Road; Camelback Road: 19th Avenue to 17th Avenue; 43rd Avenue: Virginia to McDowell Road; and 43rd Avenue: Grand Canal to Virginia Street.
Department
Responsible Department
This item is submitted by Deputy City Manager Mario Paniagua and the Street Transportation Department.