Title
Phoenix City Hall Elevator Modernization, Design-Bid-Build - 70614363 (Ordinance S-44145)
Description
Request to authorize the City Manager, or his designee, to accept Thyssenkrupp Elevator Corporation (Phoenix) as the lowest-priced, responsive and responsible bidder and enter into an agreement with Thyssenkrupp Elevator Corporation for construction services for the Phoenix City Hall Elevator Modernization project. The bids received range from a low of $4,259,758 to a high of $5,448,888, and is within the total budget for this project. Further request authorization for the City Controller to disburse all funds related to this item.
Report
Summary
Thyssenkrupp Elevator Corporation will provide construction services in support of the Phoenix City Hall Elevator Modernization project at Phoenix City Hall. The work includes, but is not limited to, a full and complete modernization of 11 gearless overhead traction passenger elevators in service since 1993. This modernization calls for the replacement of all control, dispatch, landing and power conversion systems, motor drives, governor, hoist machines, selectors, hoist ropes, governor rope, sheaves, guide assemblies, wiring, hoistway door closers and interlocks, car door operators, car door protective devices, car operating panels, position indicators, interior emergency lighting, hands free emergency communication device, hall call buttons and hall direction lanterns, and other associated work required to complete this project. To maintain building occupant access to elevator services, the modernization will be phased and limited to two elevator cars at the same time (one low-rise and one high-rise).
Procurement Information
Two bids were received according to section 34-201 of the Arizona Revised Statutes by the Street Transportation Department on Sept. 26, 2017. Both bidders were deemed responsive.
Of the three Alternates, the Public Works Department chose to select Alternate 2 and 3:
- Alternate 1 (add) is to provide a destination dispatch control system in lieu of 2-button conventional Group Automatic control
- Alternate 2 (add) is to modernize two elevators simultaneously on the low-rise in lieu of the base case
- Alternate 3 (deduct) is to omit interim and warranty periods for elevators 12 and 13
The bids (Base bid plus Alternate 2 and 3) range from a low of $4,259,758 to a high of $5,448,888. The Engineer's estimate and the two lowest responsive, responsible bidders are listed below:
Engineer's Estimate (Base bid): $3,977,000
Thyssenkrupp Elevator Corporation (Base bid): $4,283,758 Alternate 2 and 3: -$24,000
Centric Elevator Corporation (Base bid): $5,195,088 Alternate 2 and 3: $253,800
Contract Term
The term of the contract is 610 calendar days from the date of issuance of the Notice to Proceed. Contract work scope identified and incorporated into the contract prior to the end of the contract may be agreed to by the parties, and work may extend past the termination of the contract. No additional contract work scope changes may be executed after the end of the contract term.
Financial Impact
The bid award amount is within the total budget for this project. Funding is available in the Public Works Department's Capital Improvement Program budget. Contract payments may be made up to contract limits for all rendered contract services, which may extend past the contract termination.
Small Business Outreach
A Small Business Enterprise (SBE) goal was not established for this project due to the lack of SBE subcontractor availability for specialized work.