File #: 23-1709   
Type: Ordinance-S Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 7/3/2023 Final action: 7/3/2023
Title: Deer Valley Airport Blast Pads - Design-Bid-Build Services - AV31000094 (Ordinance S-50058)
District: District 1

Title

Deer Valley Airport Blast Pads - Design-Bid-Build Services - AV31000094 (Ordinance S-50058)

 

Description

Request to authorize the City Manager, or his designee, to accept J. Banicki Construction, Inc. as the lowest-priced, responsive and responsible bidder and to enter into an agreement with J. Banicki Construction, Inc. for Design-Bid-Build Services for the Deer Valley Airport Blast Pads project. Further request to authorize the City Controller to disburse all funds related to this item. The fee for services will not exceed $1,701,693.70.

 

Report

Summary

The purpose of this project is to construct four new asphalt blast pads with markings at Phoenix Deer Valley Airport. Work will include demolition and removal of two existing blast pads on Runway 7R/25L and construction of new blast pads at each end of that runway and Runway 7L/25R. Notable details include removal, storage, and relaying of rock mulch, lime treatment of soil, and electrical and lighting work associated with runway lighting.

 

J. Banicki Construction, Inc.'s services include, but are not limited to: preparing soil for expansion of south runway (7R/25L) blast pads, mill existing asphalt blast pads two inches, and installation of new larger blast pads; excavate, prepare soil, and install new blast pads on north runway (7L/25R); remove and re-install existing hardscape decomposed granite; modify existing electrical systems, as required; utilize barricades, as required; coordinate with Deer Valley Airport Operations; and other miscellaneous contract work.

 

The selection was made using an Invitation for Bids procurement process set forth in section 34-201 of the Arizona Revised Statutes. Two bids were received on May 31, 2023, and were sent to the Equal Opportunity Department for review to determine subcontractor eligibility and contractor responsiveness in demonstrating responsiveness to Disadvantaged Business Enterprise (DBE) program requirements.

 

The Opinion of Probable Cost and the lowest responsive, responsible bidders are listed below:

 

  • Opinion of Probable Cost: $1,111,429.50
  • J. Banicki Construction, Inc.: $1,701,693.70

 

Bidders who were deemed non-responsive are listed below, in alphabetical order:

 

  • Desert Services International, Inc.

 

Although the bid exceeds the Engineer’s Opinion of Probable Cost by more than 10 percent, it has been determined that the bid represents a fair and reasonable price for the required work scope. Additionally, the bid award amount is within the total budget for this project.

 

Contract Term

The term of the agreement is 180 calendar days from issuance of the Notice to Proceed. Work scope identified and incorporated into the agreement prior to the end of the term may be agreed to by the parties, and work may extend past the termination of the agreement. No additional changes may be executed after the end of the term.

 

Financial Impact

The agreement value for J. Banicki Construction, Inc. will not exceed $1,701,693.70, including all subcontractor and reimbursable costs.

 

This project will utilize federal funds and is subject to the requirements of 49 Code of Federal Regulations Part 26 and the U.S. Department of Transportation DBE program. Funding is available in the Aviation Department's Capital Improvement Program budget. The Budget and Research Department will separately review and approve funding availability prior to execution of any amendments. Payments may be made up to agreement limits for all rendered agreement services, which may extend past the agreement termination.

 

Concurrence/Previous Council Action

The City Council approved Engineering Services Agreement 155732 (Ordinance S-48243) on Jan. 5, 2022.

 