Title: Salt River Project Construction Services Contract for Relief Sewer Project: Van Buren and 52nd Streets - WS90500295 (Ordinance S-47943)
District: District 6

Title

Salt River Project Construction Services Contract for Relief Sewer Project: Van Buren and 52nd Streets - WS90500295 (Ordinance S-47943)

 

Description

Request to authorize the City Manager, or his designee, to enter into a Construction Services Contract with Salt River Project to temporarily disconnect facilities and provide construction access to the City for installation of a new sewer line. Further request to grant an exception pursuant to Phoenix City Code 42-20 to authorize inclusion in the documents pertaining to this transaction of indemnification and assumption of liability provisions that otherwise would be prohibited by Phoenix City Code 42-18. Additionally, request to authorize the City Controller to disburse all funds related to this item. The total value of the contracts will not exceed $14,179.40.

 

Report

Summary

The City is constructing a new sewer line on Van Buren Street from 52nd Street to Galvin Parkway and construction activity will be taking place in close proximity to existing streetlights. For safety purposes, Salt River Project (SRP) will temporarily disconnect overhead streetlights and provide temporary lighting for the duration of the disconnect. The total cost of work for the Construction Services Contract is $14,179.40. This work is in conjunction with City Project WS90500295 Relief Sewer Project; Van Buren and 52nd streets.

 

Contract Term

The term of the contract will begin late August 2021 and will expire when the streetlights are reinstalled and reenergized.

 

Financial Impact

Funding in the amount of $14,179.40 is available in the Water Services Department Capital Improvement Program budget.

 

Location

Van Buren Street: 52nd Street to Galvin Parkway.

Council District: 6

 

Department

Responsible Department

This item is submitted by Deputy City Managers Mario Paniagua and Karen Peters, and the Street Transportation and Water Services departments.