File #: 22-2155   
Type: Payment Ordinance Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 12/14/2022 Final action: 12/14/2022
Title: Archer Western Construction, LLC

Title

Archer Western Construction, LLC

 

Description

For $386,503.16 in additional payment authority for Contract 154493, Change Order 1 for Project WS90500302-4 for the 38th Street Relief Sewer: Phase 2 - 38th Street Design/Bid/Build for the Water Services Department. The change order is for unforeseen changes for hard rock excavation: traffic control devices; extra asphalt removal and replacement; remove and replace sidewalk; sawcut and remove Asphalt Concrete pavement; placement of 24-inch Corrugated Metal Pipe storm drain; additional sewer manhole; hard rock excavation unit price negotiation; new river rock; and additional landscaping requested by the effected homeowners association. The work was not included as part of the original bid. The project will use Water Services Department Capital Improvement funds.