Title
Spray Systems of Arizona, Inc.
Description
For $57,680 in additional payment authority for Contract 159019, Change Order 1 (AH20300003) for the Edison Impact Hub Abatement and Demolition, for the Housing Department. This Change Order is necessary for removal and disposal of unforeseen asbestos containing materials and additional abatement time. This work was not included as part of the original bid. This project uses American Rescue Plan Act (ARPA) funds. There is no impact to the General Fund.