File #: 18-0007   
Type: Ordinance-S Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 4/18/2018 Final action: 4/18/2018
Title: 2017 PVC-Lined Concrete Sewer Pipe and Manhole Rehabilitation, North - Construction Manager at Risk Construction Phase Services - WS90500272 (Ordinance S-44450)
District: District 1, District 2, District 3
Related files: 17-5643

Title

2017 PVC-Lined Concrete Sewer Pipe and Manhole Rehabilitation, North - Construction Manager at Risk Construction Phase Services - WS90500272 (Ordinance S-44450)

 

Description

Request to authorize the City Manager, or his designee, to enter into an agreement with Achen-Gardner Construction, LLC to provide Construction Manager at Risk (CMAR) Construction Phase Services in support of the 2017 PVC-lined concrete sewer pipe and manhole rehabilitation project in multiple locations within the City of Phoenix rights-of-way or easements, generally located north of Dunlap Avenue. Further request authorization to execute amendments to the contract as necessary within the Council-approved expenditure authority as provided below, and for the City Controller to disburse all funds related to this item. The fee for services will not exceed $26,540,519, including all subcontractor and reimbursable costs.

 

Report

Summary

The PVC-Lined Concrete Sewer Condition Assessment Report dated April 2017 recommended rehabilitation of 71 sewer pipe segments totaling approximately 44,000 feet (8.3 miles) at various City locations and rehabilitation of 190 manholes. Sewer pipeline rehabilitation may include spot repairs of PVC lining or cured-in-place pipe (CIPP) lining of pipe segments from manhole to manhole. Manhole rehabilitation may include coating restoration, lining repair, structural inserts or replacement. In addition, complex wastewater bypass systems will be required to complete some of the work.

 

Achen-Gardner Construction, LLC's initial contract services will include preparation of a Guaranteed Maximum Price (GMP) proposal for the construction services provided under the contract and participating with the City in a process to achieve the local and Small Business Enterprise (SBE) goal of 2 percent that was set for the project. Achen-Gardner Construction, LLC will be required to solicit bids from prequalified subcontractors and to perform the work using the City's subcontractor selection process. Achen-Gardner Construction, LLC may also compete to self-perform limited amounts of work.

 

Achen-Gardner Construction, LLC will then assume the risk of delivering the project through the GMP. The construction services include, but are not limited to: bidding, awarding and managing subcontractors; preparing necessary GMP proposals; and implementing the rehabilitation solutions determined in the pre-construction phase.

 

Procurement Information

Achen-Gardner Construction, LLC was chosen for this project using a qualifications-based selection process according to section 34-603 of the Arizona Revised Statutes. Scoring and selection were made in conjunction with the CMAR Design Phase Services Contract.

 

Contract Term

The term for services is expected to be three years after issuance of the Notice to Proceed. Contract work scope identified and incorporated into the contract prior to the end of the contract term may be agreed to by the parties and work may extend past the termination of the contract. No additional contract work scope may be executed after the end of the contract term.

 

Financial Impact

Staff will execute the initial contract for GMP preparation services for a fee not-to-exceed $50,519, including subcontractor and reimbursable costs. Contract amendments may be executed for GMP services or other contract services totaling an amount not-to-exceed the remaining $26,490,000, for a total contract amount of $26,540,519. Contract amendments will be reviewed and approved separately by the Budget and Research Department. Funds are available in the Water Services Department's Capital Improvement Program budget. Contract payments may be made up to the contract limits for all rendered contract services, which may extend past the contract termination.

 

Concurrence/Previous Council Action

The City Council approved the CMAR Design Phase Services Contract 147089 (Ordinance S-44338) on March 21, 2018.

 

Location

The project is located in various City of Phoenix rights-of-way or easements, which are generally north of Dunlap Avenue.

Council Districts: 1, 2, 3

 

Department

Responsible Department

This item is submitted by Deputy City Managers Karen Peters and Mario Paniagua, the Water Services Department, and the City Engineer.