Title
Low Mountain Construction, Inc.
Description
For $43,381.00 in additional payment authority for Agreement 152339, for Change Order 1, Project 8640600010 for the Edison Park Activity Hub Project for the Housing Department. The additional funds include a partial redesign of the ramada structures, stage roofs, and substructures due to constructability issues and to cover the extension of the project schedule. The change order includes extra work in materials and shop drawings to provide the modified ramada design and painting, costs for extended general conditions, and a credit back for removing the powder coating. The items were enhancements to the original design, necessary to meet code compliance and improve life safety issues. The project will use federal Housing and Urban Development funds. No General Funds are being used.