Title
Cave Creek and Lone Mountain Waterline Connection - Construction Manager at Risk Services Amendment - WS85100032 (Ordinance S-52844) - District 2
Description
Request to authorize the City Manager, or his designee, to execute an amendment to Agreement 155550 with Garney Companies, Inc. to provide additional Construction Manager at Risk Construction Services for the Cave Creek and Lone Mountain Waterline Connection project. Further request to authorize execution of amendments to the agreement as necessary within the Council-approved expenditure authority as provided below, and for the City Controller to disburse all funds related to this item. The additional fee for services included in this amendment will not exceed $2 million.
Report
Summary
The purpose of this project is to construct approximately one mile of new waterline to connect between existing infrastructure south of Carefree Highway and the new 10A-B1 Booster Pump Station (BPS). Approximately one mile of new waterline will also be constructed along Lone Mountain Road for system resiliency when the BPS is operational.
This amendment is necessary because of unforeseen field conditions along Lone Mountain Road requiring additional spending authority and time. This amendment will provide additional funds and time to the agreement.
Contract Term
The term of the agreement amendment is one year from the issuance of the amendment Notice to Proceed. Work scope identified and incorporated into the agreement prior to the end of the term may be agreed to by the parties, and work may extend past the termination of the agreement. No additional changes may be executed after the end of the term.
Financial Impact
- The initial agreement for Construction Manager at Risk Services was approved for an amount not to exceed $14,050,000, including all subcontractor and reimbursable costs.
- An amendment increased the agreement by an additional $4,850,000, for a new total amount not to exceed $18.9 million, including all subcontractor and reimbursable costs.
- This amendment will increase the agreement by an additional $2 million, for a new total amount not to exceed $20.9 million, including all subcontractor and reimbursable costs.
Funding for this amendment is available in the Water Services Department's Capital Improvement Program budget. The Budget and Research Department will separately review and approve funding availability prior to the execution of any amendments. Payments may be made up to agreement limits for all rendered agreement services, which may extend past the agreement termination.
Concurrence/Previous Council Action
The City Council approved:
- Construction Manager at Risk Preconstruction Services Agreement 153443 (Ordinance S-47136) on December 2, 2020.
- Construction Manager at Risk Construction Services Agreement 155550 (Ordinance S-48093) on November 17, 2021.
- Construction Administration and Inspection Services Agreement 156012 (Ordinance S-48396) on March 23, 2022.
- Amendment to Construction Manager at Risk Construction Services Agreement 155550 (Ordinance S-50592) on February 21, 2024.
Location
Cave Creek Road between Lone Mountain Road and Carefree Highway and Lone Mountain Road between Cave Creek Road and 56th Street
Council District: 2
Department
Responsible Department
This item is submitted by Assistant City Manager Ginger Spencer, Deputy City Manager Amber Williamson, the Water Services Department and the City Engineer.