Water System Redundancy Project Phase I Construction Administration and Inspection Services - WS85470002 (Ordinance S-44415)
Description
Request to authorize the City Manager, or his designee, to execute an agreement with Carollo Engineers, Inc. to provide construction administration and inspection (CA&I) services in support of the Water System Redundancy Project Phase I. The fee for services will not exceed $1.9 million. Further request authorization for the City Controller to disburse all funds related to this item.
Report
Summary
Phase I of this project is to implement standby power systems at Phase I facilities including the Cave Creek Corridor Booster Pump Stations (6A-B1, 7A-B1, and 8A-B1), the Union Hills Water Treatment Plant (WTP) pressure zone 5E, and the Deer Valley WTP pressure zones 1, 2A, and 3D finished water booster pumps. This project will also develop a roadmap for implementing power redundancy in future phases to maintain potable water production at the Union Hills, Deer Valley, 24th Street, and Val Vista WTPs. Providing power redundancy at these facilities will improve the City's ability to continue potable water deliveries to customers during potential local or regional utility outages.
Carollo Engineers, Inc.'s CA&I services include, but are not limited to: providing project administration and engineering services during construction activities, inspecting the site through various stages of construction, reviewing contractor work submittals, performing field inspections where required for completed repairs, and providing resident services during construction.
Procurement Information
Carollo Engineers, Inc. was chosen for this project using a qualifications-based selection process according to Section 34-603 of the Arizona Revised Statutes.
Contract Term
The contract term is for three years from the date of the Notice to Proceed. Contract work scope identified and incorporated into the contract prior to the end of the contract may be agreed to by the parties, and work may extend past the termination for work in progress. No additional contract work scope changes may be executed after the end of the contract term.
Financial Impact
Carollo Engineers, Inc.'s fee under the contract will not exceed $1.9 million, which includes all subconsultant and reimbursable costs. Funding is available in the Water Services Department's Capital Improvement Program budget. Contract payments may be made up to contract limits for all rendered contract services, which may extend past the contract termination.
Location
Facilities included in this project are located on Cave Creek Road between Pinnacle Peak Road and Dixileta Drive (Cave Creek Corridor Booster Pump Stations) and at the Union Hills and Deer Valley Water Treatment Plants.
Council Districts: 1, 2
Department
Responsible Department
This item is submitted by Deputy City Managers Karen Peters and Mario Paniagua, the Water Services Department, and the City Engineer.