Title
Stantec Consulting Services Inc.
Description
For $120,000.00 in additional payment authority for Agreement 148833 for Change Order 3, AV02000033 Phoenix Sky Harbor International Airport Terminal 2 Processor and Garage Demolition Project for the Aviation Department. Additional spending authority is needed to provide additional construction administration and inspection services to extend the construction oversight of the contractor due to material supply delays as well as to improve pedestrian and traffic safety. The project is necessary to complete the demolition of Terminal 2 and to construct a new operations parking area and pedestrian walkway from the west economy parking area to connect to the existing pathway to the Terminal 3 Sky Train Station.