File #: 17-2159   
Type: Ordinance-S Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 4/19/2017 Final action: 4/19/2017
Title: Val Vista Transmission Main Rehabilitation - Construction Manager at Risk Construction Phase - GMP Preparation Services - WS85500437 (Ordinance S-43440)
District: Out of City
Related files: 18-1256

Title

Val Vista Transmission Main Rehabilitation - Construction Manager at Risk Construction Phase - GMP Preparation Services - WS85500437 (Ordinance S-43440)

 

Description

Request to authorize the City Manager, or his designee, to enter into a contract with Achen-Gardner Construction, LLC, (Chandler, Ariz.) to provide Construction Manager at Risk (CMAR) Construction Phase Guaranteed Maximum Price (GMP) Preparation Services for the Val Vista Transmission Main Rehabilitation - 2016 project. Further request authorization for the City Controller to disburse all funds related to this item.

 

Report

Summary

The Val Vista water transmission main includes pipe sizes ranging from 72 inches to 108 inches in diameter. A scoping analysis was completed on the Val Vista transmission main in 2016, which determined that the first four sections of the transmission main require slip-lining. Additional sections will be rehabilitated in future construction phases.

 

Achen-Gardner Construction, LLC, will assume the risk of delivering the project through a GMP contract. The CMAR will be responsible for construction means and methods, participation with the City in a process to set goals for local and Small Business Enterprise (SBE) participation, and implementation of the local and SBE processes. The SBE goal will be established prior to construction. The CMAR will also be required to solicit bids from prequalified subcontractors and to perform the work using the City’s subcontractor selection process. The CMAR may also compete to self-perform limited amounts of work.

 

Procurement Information

Achen-Gardner Construction, LLC, was chosen to provide CMAR Services for this project using a qualifications-based selection process according to Section 34-603 of the Arizona Revised Statutes (ARS). Scoring and selection were made in conjunction with the CMAR Design Phase Services.

 

Contract Term

The term for GMP preparation services portion of this contract is expected to take approximately one year. The CMAR Construction Services will be implemented under an amendment to this contract. Contract work scope identified and incorporated into the contract prior to the end of the contract may be agreed to by the parties, and work may extend past the termination of the contract. No additional contract work scope changes may be executed after the end of the contract term.

 

Financial Impact

Achen-Gardner Construction, LLC's fee for GMP preparation services will not exceed $24,973.78 including all subcontractor, supplier and reimbursable costs. Funding is available in the Water Services Department's Capital Improvement Program (CIP) budget. Contract payments may be made up to the contract limits for all rendered contract services, which may extend past the contract termination.

 

Concurrence/Previous Council Action

The CMAR Design Phase contract is being submitted for City Council approval simultaneously with this request for CMAR Construction Phase GMP Preparation Services contract.

 

Location

Bass Pro Drive and Alma School Road (Mesa, Ariz.)

North Country Club Drive and West Juniper Street (Mesa, Ariz.)

West Juniper Street and Grand (Mesa, Ariz.)

 

Department

Responsible Department

This item is submitted by Deputy City Managers Karen Peters and Mario Paniagua, the Water Services Department and the City Engineer.