File #: 18-0989   
Type: Ordinance-S Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 5/16/2018 Final action: 5/16/2018
Title: Lift Station 40 Refurbishment - Construction Manager at Risk Design Phase Services - WS90400085 (Ordinance S-44567)
District: District 6

Title

Lift Station 40 Refurbishment - Construction Manager at Risk Design Phase Services - WS90400085 (Ordinance S-44567)

 

Description

Request to authorize the City Manager, or his designee, to enter into an agreement with Felix Construction Company to provide Construction Manager at Risk (CMAR) Design Phase Services in support of the Lift Station 40 Refurbishment project located at I-10 and Ray Road. Further request authorization for the City Controller to disburse all funds related to this item. The fee for services will not exceed $52,000.

 

Report

Summary

Lift Station 40 conveys wastewater north approximately three miles to a gravity sewer at Guadalupe Road east of 48th Street. The current lift station pump capacity is approximately 13 million gallons per day. The four currently-installed sewage pumps cannot operate at full speed due to age and require replacement.

 

Felix Construction Company will begin in an agency support role for Design Phase Services and then hold the construction contract with the City for construction of the project.

 

Services during the CMAR design phase will include, but are not limited to: field inspections as necessary for full understanding of required rehabilitation, including needs for maintaining lift station in service during construction; providing detailed cost estimating and identification of marketplace conditions; planning and scheduling project and construction phases to minimize interruption to City operations; evaluating alternate systems; providing constructability studies; advising on potential efficiencies in project delivery; performing and initiating long-lead studies and procurements; assisting in permitting processes; and participating in the Small Business Enterprise (SBE) process to establish the SBE goal prior to construction.

 

Procurement Information

Felix Construction Company was chosen for this project using a qualifications-based selection process according to section 34-603 of the Arizona Revised Statutes (A.R.S.). Pursuant to A.R.S. title 34, the City may not release the scoring of proposers until a contract has been awarded. Five firms submitted proposals. The top three rankings follow:

 

Felix Construction Company: Rank 1

MGC Contractors, Inc.: Rank 2

CSW Contractors, Inc.: Rank 3

 

Contract Term

The term for CMAR Design Phase services is expected to be 18 months after issuance of the Notice to Proceed. Contract work scope identified and incorporated into the contract prior to the end of the contract may be agreed to by the parties and work may extend past the termination of the contract. No additional contract work scope may be executed after the end of the contract term.

 

Financial Impact

Felix Construction Company's fee for contract services will not exceed $52,000, including all subconsultant, subcontractor, and reimbursable costs. Funding for these services is available in the Water Services Department's Capital Improvement Program budget. Contract payments may be made up to the contract limits for all rendered contract services, which may extend past the contract termination.

 

Location

The project is located in the area of 51st Street and Ray Road.

Council District: 6

 

Department

Responsible Department

This item is submitted by Deputy City Managers Karen Peters and Mario Paniagua, the Water Services Department, and the City Engineer.