File #: 21-2842   
Type: Payment Ordinance Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 1/5/2022 Final action: 1/5/2022
Title: Sundt Construction, Inc.

Title

Sundt Construction, Inc.

 

Description

For $1,503,257.00 in additional payment authority for Contract 151260, Change Order 1 for Project WS85230052 for the Val Vista Water Treatment Plant Rehabilitation 2018 project for the Water Services Department. The change order is for new scope which includes electrical building re-sequencing, Used Water Recovery System backwash clarifier coating rehabilitation, and final sediment basins grout repair. The work was not included as part of the original bid. All unused funds will be placed in owner's contingency. The project uses funds from the Water Services Department's Capital Improvement budget; no General Funds are required.