For $19,515.42 in additional payment authority for Agreement 147769, for Change Order 3 for Project ST87600121 Oak Street: 3rd Street to Grand Canal Bike and Pedestrian Improvements project for the Street Transportation Department. This change order is to provide additional design services including a change from a Rapid Rectangular Flashing Beacon to a three-way stop at 20th Street and Oak Street. The change of design is due to adjacent City and development projects along the project corridor and an additional design submittal at the request of City staff. This work was not included as part of the original proposal.