Title
G & G Specialty Contractors, Inc.
Description
For $80,128.71 in additional payment authority for Contract 146649, Change Order 4 (Project AH10150006-D), Pine Tower Apartments Phase II for the Housing Department. Change order is for large studio renovations and community room improvements; additional services to perform point-to-point grounding test per City of Phoenix electrical inspector; install new gas line from existing boiler room to new laundry room addition; replace copper water line from chiller room to new laundry room addition; install new electrical feeders from chiller room to community center panel; and saw cut and replace various areas of concrete. This work was not included as part of the original bid. This project uses Housing and Urban Development funds; no General Funds are required.