Title
Salt River Project Distribution Design and Construction Contracts for Installation of Traffic Signal Improvements at 51st Avenue and Indian School Road, and 71st Avenue and Thomas Road - ST89340584 (Ordinance S-49554)
Description
Request to authorize the City Manager, or his designee, to enter into two Distribution Design and Construction Contracts with Salt River Project for the design and construction of electrical facilities at 51st Avenue and Indian School Road, and 71st Avenue and Thomas Road for City of Phoenix Project ST89340584. Further request to grant an exception pursuant to Phoenix City Code 42-20 to authorize inclusion in the documents pertaining to this transaction of indemnification and assumption of liability provisions that otherwise should be prohibited by Phoenix City Code 42-18. Additionally request to authorize the City Controller to disburse all funds related to these items. The total value of the contracts will not exceed $27,004.02.
Report
Summary
The City is constructing traffic signal improvements at the intersections of 51st Avenue and Indian School Road, and 71st Avenue and Thomas Road, which will require the design and construction of new electrical facilities at both locations. These contracts represent the costs for Salt River Project's design and construction to provide power services to the new traffic signals.
Contract Term
The contracts will begin on or about April 6, 2023, and will end in one year.
Financial Impact
Funding in the amount of $27,004.02 is available in the Street Transportation Department's Capital Improvement Program budget.
Location
51st Avenue and Indian School Road, and 71st Avenue and Thomas Road.
Council Districts: 4, 5, 7
Department
Responsible Department
This item is submitted by Deputy City Manager Alan Stephenson, the Street Transportation Department, and the City Engineer.