File #: 20-0781   
Type: Ordinance-S Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 5/20/2020 Final action: 5/20/2020
Title: 16-Inch Paradise Valley Zone 3C Improvements - Construction Administration and Inspection Services Amendment 1 - WS85500418 (Ordinance S-46611)
District: District 3, Out of City
Related files: 18-3095

Title

16-Inch Paradise Valley Zone 3C Improvements - Construction Administration and Inspection Services Amendment 1 - WS85500418 (Ordinance S-46611)

 

Description

Request to authorize the City Manager, or his designee, to execute an amendment to Agreement 148835 with Entellus, Inc. to provide funding for Construction Administration and Inspection (CA&I) Services for the 16-Inch Paradise Valley Zone 3C Improvements project. Further request to authorize execution of amendments to the agreement as necessary within the Council-approved expenditure authority as provided below, and for the City Controller to disburse all funds related to this item. The additional fee for services included in this amendment will not exceed $472,531.

 

Report

Summary

The purpose of this project is to design approximately 21,500 linear feet of 16-inch Ductile Iron Pipe transmission main within Pressure Zone 3C in the Town of Paradise Valley, and a new Pressure Reducing Valve Station (PRV) proposed to be located within Pressure Zone 4A on an existing City of Phoenix retention basin property on the southwest corner of Shea Boulevard and 45th Place. This will relieve Booster Station 3C-B1 and Well 235, which are located southwest of Invergordon and Doubletree Ranch roads. The new 16-inch transmission main will connect to the existing 16-inch transmission main within Shea Boulevard.

 

This amendment is necessary to include funding for CA&I services for the project. This amendment will provide additional funds and time to the agreement. This agreement is essential to the health, safety, and welfare of the public and critical operations for the City.

 

Contract Term

The term of the agreement amendment is 248 calendar days from issuance of the Notice to Proceed. Work scope identified and incorporated into the agreement prior to the end of the term may be agreed to by the parties, and work may extend past the termination of the agreement. No additional changes may be executed after the end of the term.

 

Financial Impact

  • The initial agreement for Engineering Services was authorized for a fee not-to-exceed $1.3 million, including all subconsultant and reimbursable costs.
  • Amendment 1 will increase the agreement by an additional $472,531, for a new total not-to-exceed agreement value of $1,772,531, including all subconsultant and reimbursable costs.

 

Funding for this amendment is available in the Water Services Department's Capital Improvement Program budget. The Budget and Research Department will separately review and approve funding availability prior to the execution of any amendments. Payments may be made up to agreement limits for all rendered agreement services, which may extend past the agreement termination.

 

Concurrence/Previous Council Action

The City Council approved:

  • Engineering Services Agreement 148835 (Ordinance S-45144) on Nov. 14, 2018.

 

Location

  • Shea Boulevard from 45th Place to Tatum Boulevard
  • Tatum Boulevard from Shea Boulevard to Doubletree Ranch Road
  • Doubletree Ranch Road from Tatum Boulevard to 56th Street
  • 56th Street from Doubletree Ranch Road to Mockingbird Lane
  • Mockingbird Lane from 56th Street to Invergordon Road

Council District: 3 and Out of City

 

Department

Responsible Department

This item is submitted by Deputy City Managers Karen Peters and Mario Paniagua, the Water Services Department, and the City Engineer.