Legislation Details

File #: 22-0880   
Type: Information Only Status: Agenda Ready
Meeting Body: Transportation, Infrastructure, and Planning Subcommittee
On agenda: 6/15/2022 Final action:
Title: Freeway Program Update
District: Citywide

Title

Freeway Program Update

 

Description

This report provides the Transportation, Infrastructure and Planning Subcommittee updates on the Arizona Department of Transportation (ADOT) freeway program within the City of Phoenix.

 

THIS ITEM IS FOR INFORMATION ONLY.

 

Report

Summary

The Maricopa Association of Governments (MAG) Regional Transportation Plan reflects numerous freeway construction projects and studies underway within the City of Phoenix. These projects are funded from the voter approved Proposition 400 half-cent sales tax as well as from state and federal revenue sources. City of Phoenix staff are embedded with ADOT on these major construction projects to ensure coordination of all construction activities with City departments. This report is an overview of the current major freeway projects. A monthly report will be provided to the Transportation, Infrastructure and Planning Subcommittee reflecting project changes as well as new projects.

 

Interstate 10 (I-10) - Broadway Curve Reconstruction

The I-10 Broadway Curve project is planned to improve a segment of I-10 between the I-10/Interstate 17 (I-17) Split Traffic Interchange and the South Mountain Freeway/Congressman Ed Pastor Freeway Loop 202 near Pecos Road. The project encompasses one of the most heavily traveled segments of freeway in the Valley. Traffic volumes within this 11-mile section of I-10 exceed 250,000 vehicles per day and include vital connections to I-17, State Route (SR) 143, US-60 and Loop 202.

 

The proposed improvements include:

  • Adding general purpose and High Occupancy Vehicle (HOV) lanes;
  • Adding a collector-distributor road system to reduce the number of lane changes on the freeway;
  • Improving connections between I-10 and the SR 143 and Broadway Road to improve HOV lane connections;
  • Improving connections of I-10 and US-60 (Superstition Freeway);
  • Constructing new bridges to accommodate new interchange facilities and additional lanes;
  • Building retaining and sound walls; and
  • Constructing pedestrian bridge crossings to improve pedestrian access across the freeway.

 

Construction began in late 2021 and is scheduled for completion in 2024.

 

Update:

  • ADOT achieved a major milestone in May when crews began building the first bridge “superstructure.” The superstructure is the part vehicles will drive across, and rests on the piers and abutments, which are known as the “substructure.” The work occurred over three nights on the east side of northbound SR 143. A crane lifted and placed 25 box-shaped beams (box beams) for the bridge over the Tempe Drain on 48th Street and on a section of northbound SR 143 that is being widened. Each of the box beams weighed up to 40,000 pounds.
  • Crews began drilling the foundation for a new bridge next to the ramp that connects westbound US-60 (Superstition Freeway) to westbound I-10.
  • Construction of new sound walls between Guadalupe and Elliot roads is underway.
  • In June, crews plan to set the girders for the new bridges over I-10 at 48th Street and place the box beams for the bridge over the Tempe Drain on southbound SR 143. Later in June and July, workers expect to set the girders for the new bridge over I-10 at Broadway Road.

 

I-10 - I-17 to Avondale Boulevard Pavement Improvement

This project is to extend the life of the pavement and improve the driving experience on I-10 from I-17 to Avondale Boulevard. This project was initiated by ADOT to address the potholes and uneven pavement in this corridor.

 

The major elements of this project include removing the existing asphalt pavement and using a diamond grinding treatment to provide a smooth roadway surface. The recently-installed section of rubberized asphalt on I-10 near the connection to the Loop 202 freeway between 43rd and 67th avenues will not be removed. An additional travel lane on westbound I-10 between 67th Avenue and Avondale Boulevard will be added by reducing the shoulder and lane widths. The striping on the southbound Loop 101 ramp to westbound I-10 will be modified to create two lanes.

 

There will be regular weekend closures and overnight lane restrictions on I-10 during the year-long construction project.

 

Construction began in September 2021 and will conclude in late 2022.

 

I-17 Frontage Road Drainage Improvement

This ADOT project will replace the existing pump stations at the I-17 traffic interchanges at Greenway Road, Thunderbird Road, Cactus Road and Peoria Avenue with a gravity storm drain system that will discharge the storm water into the Arizona Canal Diversion Channel (ACDC). The purpose of the project is to improve the drainage facilities that remove storm runoff from the cross streets, helping to reduce the potential for flooding at the I-17 overpasses.

 

The project includes the installation of 30- to 90-inch diameter reinforced concrete pipe along the I-17 frontage road, two detention basins at the I-17 and Thunderbird Road traffic interchange, pavement replacement on the frontage road, signing, striping, improvements to ADA features within the project area, and removal of the four existing pump stations.

 

Construction began in January 2020 and is expected to conclude in late 2022.

 

Update:

  • ADOT has notified the City that there will be continued closures of Greenway Road between 29th and 25th avenues, as well as weekend ramp closures at Greenway Road for several weeks, as work continues on a regional drainage system project. The work will require closing westbound Greenway Road between 29th and 25th avenues from 9:00 p.m. Friday, June 3, 2022 through late June 2022 to reconstruct the roadway. Eastbound Greenway Road will also be closed during several weekend closures of the interchange throughout June. The extended road closures will allow the concrete to cure for approximately a week before putting traffic back on the roadway.

 

Loop 101 - I-17 to 75th Avenue Widening

The scope of this project is to add one general purpose lane in each direction to Loop 101/Agua Fria Freeway from I-17 to 75th Avenue. The project includes bridge widening of existing structures to accommodate the new general-purpose lanes. The project work includes diamond grind surface treatment, new concrete pavement, retaining walls, lighting, ADA improvements, drainage improvements, FMS improvements, and signing and striping.

 

I-10 Deck Park (Hance Park) Tunnel Repair

The Deck Park Tunnel is an underpass that carries the I-10 freeway beneath downtown Phoenix between 3rd Avenue and 3rd Street. The tunnel consists of a series of nineteen side-by-side bridge structures. Construction of the facility began in 1983 and opened to traffic on Aug. 10, 1990. The tunnel carries approximately 230,000 vehicle trips per day and provides a critical link for regional connectivity and mobility.

 

Leaks in the ceiling structure of the Deck Park Tunnel have occurred in the past and continue to appear. The water infiltration caused by the leaks can lead to deterioration of the tunnel infrastructure and impacts the ventilation and electrical systems, which could force closure of the tunnel to traffic. There is also concern that any damage could produce a need for repairs that would require excavation of Margaret T. Hance Park, which is undergoing a major, $100 million revitalization that began in March 2020.

 

ADOT, MAG and the City of Phoenix initiated an I-10 Deck Park Tunnel Waterproofing Study in May 2019 because of concern with the integrity of the tunnel.

 

The study recommended that all joints that have not been repaired in the last five years be replaced, which comprises 15 of the 19 total joints. ADOT intends on working closely with the City of Phoenix to coordinate construction activities of the joint work with the Hance Park revitalization project to minimize cost and public disturbance.

 

Construction began in March 2020.

 

US-60 (Grand Avenue) - 35th Avenue - Indian School Road Study

ADOT and the Federal Highway Administration (FHWA), in coordination with the BNSF Railway, City of Phoenix and MAG, are initiating a Draft Environmental Assessment (EA) and initial DCR for the US-60 (Grand Avenue), 35th Avenue and Indian School Road intersection.

 

The study proposes that improvements need to be made to the US-60 corridor functionality, arterial street network multimodal opportunities (e.g., expansion of bicycle lane network), and BNSF Railway corridor capacity. These improvements would reduce traffic congestion, improve pedestrian and vehicular safety and enhance multimodal transportation options.

 

This project is currently in the predesign stage through mid-2022.

 

Loop 303 - I-17 to Lake Pleasant Parkway Update

At the request of the City of Phoenix, MAG and ADOT are conducting a DCR Update for Loop 303 from I-17 to Lake Pleasant Parkway. A 2006 DCR identified the ultimate footprint and alignment for Loop 303. The purpose of this project is to prepare a DCR update and environmental document for additional general-purpose lanes in each direction of travel. The update includes establishing new traffic models and developing, evaluating, and costing conceptual alternatives for the improvements including Traffic Interchanges (TIs) at 67th, 51st, and 43rd Avenues, as well as the system interchange at I-17. The existing Loop 303 was constructed to accommodate the future construction of these TIs.

 

Phoenix, MAG, and ADOT have agreed to accelerate design and construction of the new TIs at 51st and 43rd Avenues to accommodate the schedule of the new Taiwan Semiconductor Manufacturing Company (TSMC) facility. Construction of the new TIs will be completed in summer 2023.

 

Department

Responsible Department

This item is submitted by Deputy City Manager Mario Paniagua and the City Manager’s Office.