Title
Salt River Project Distribution Design and Construction Contract - ST85160015 - Thomas Road, 51st to 43rd Avenues (Ordinance S-53290) - District 4
Description
Request to authorize the City Manager, or his designee, to enter into a Distribution Design and Construction Contract with Salt River Project for project ST85160015. Further request to grant an exception pursuant to Phoenix City Code 42-20 to authorize inclusion in the documents pertaining to this transaction of indemnification and assumption of liability provisions that otherwise should be prohibited by Phoenix City Code 42-18. Further request authorization for the City Controller to disburse all funds related to this item in an amount not to exceed $84,813.69.
Report
Summary
The City is installing new streetlights on Thomas Road from 51st to 43rd avenues. The contract is for the design and construction of electrical associated with the City project.
Contract Term
The term of the agreement will begin on or about November 4, 2026, and will expire when the project is completed and accepted.
Financial Impact
The agreement will not exceed $84,813.69. Funding is available in the Street Transportation Department's Capital Improvement Program budget.
Location
Thomas Road; 51st to 43rd avenues.
Council District: 4
Department
Responsible Department
This item is submitted by Deputy City Manager Frank McCune and the Street Transportation Department.