Title: Combs Construction Company, Inc.

Title

Combs Construction Company, Inc.

 

Description

For $350,000.00 in additional payment authority for Agreement 145067 for Change Order 1, Project ST87600074 for the Grand Canalscape Phase I Uptown, Gateway North from 15th Avenue to 16th Street, and 36th Street to 40th Street for the Street Transportation Department. This request for additional payment authority includes work on Grand Canalscape related to unforeseen conditions such as additional vegetation removal, canal shoulder grading, and remediation of unsuitable subgrade soil material. Additionally, in some locations, it was necessary to modify planned light poles to bollard-style lights due to space constraints and provide additional lighting in other locations. This work was not originally included in the contract.