File #: 17-1799   
Type: Ordinance-S Status: Adopted
Meeting Body: City Council Formal Meeting
On agenda: 4/5/2017 Final action: 4/5/2017
Title: Economic Impact Analysis for Margaret T. Hance Park (Ordinance S-43374)
District: District 7

Title

Economic Impact Analysis for Margaret T. Hance Park (Ordinance S-43374)

 

Description

Request to authorize the City Manager, or his designee, to enter into a contract with Hunden Strategic Partners, Inc., to develop an economic impact analysis for Margaret T. Hance Park.

 

Report

Summary

The purpose of this study is to develop objective economic data to inform potential sponsors and donors regarding the future economic impact of a fully implemented Hance Park Master Plan. The economic data will be used to assist the City's partners in solicitation of private and non-profit partnerships to be able to realize Hance Park's development.

 

Three proposals were received by the Parks and Recreation Department for the Request for Proposal (RFP) issued on Nov. 28, 2016 for the economic impact analysis for Margaret T. Hance Park.  Following is the tabulation of the proposal scores received:

 

Applied Economics: 66

HR & A Advisors: 84

Hunden Strategic Partners: 90

 

Contract Term

The agreement term is for one year.

 

Financial Impact

Cost for the economic impact analysis will not exceed $50,000, and includes all consultants, subcontractor and reimbursable costs.  Funds are available from the Parks and Recreation Department's Capital Improvement Program budget utilizing Phoenix Parks and Preserves Initiative funds.

 

Concurrence/Previous Council Action

This item was heard at the March 22, 2017 Parks, Arts, Education and Equality Subcommittee, and approval recommended by a vote of 4-0.

 

Location

Margaret T. Hance Park is a 32-acre public park located at 67 W. Culver St.

 

Department

Responsible Department

This item is submitted by Deputy City Manager Deanna Jonovich and the Parks and Recreation Department.